Fuel Cost Planning Saves Project $

The CCHS Building Committee pre-purchased 200,000 gallons of propane @ $1.80 in September to lock in favorable pricing to heat the new high school building while temperature sensitive materials were installed during winter months.  This planning has saved the project an estimated $100,000 as propane prices have risen to $2.80.CCHS-2-26-14