Construction Update 6/1/13

The construction team continues foundation work which consists of concrete pours for foundations and walls as well as placing rebar.  The team is currently placing the foundation along the south elevation of what will be gymnasium of the new school building.  This activity will continue for the next several weeks as foundation operations will complete the perimeter of the new building.

 The temporary access road to the athletic field is complete and paved.  Work continues on the grades to the east of the existing building to create a road to facilitate construction and a retaining area.  Trenches are being excavated to begin utility work to the south of the new building site.  All construction activities remain on schedule.   

 