April 2009
Voters approve Master Plan for CCHS
April 2010
Voters approve Feasibility Study and Schematic Design for CCHS
Sept. 2010
CCHS is invited to participate in the Massachusetts School Building Authority’s program for reimbursement June 2011 Feasibility study completed
Aug. 16, 2011
Schematic Design completed and approved by CCHS Building Committee
Aug. 19, 2011
Schematic Design is submitted to MSBA for approval
Sept. 28, 2011
MSBA Board meets and approves CCHS project for funding
Nov. 2011
The towns of Concord and Carlisle vote and overwhelmingly approve CCHS project at Town Meetings and polls
Early 2012
Work begins on Detailed Design, Construction Manager is hired
Aug. 2012
Detailed Design complete, work begins on construction drawings, early bid packages prepared
October 2012
work on Construction Documents begins
Jan-March 2013
Construction starts
- 60% Documents delivered to MSBA – End of January 2013
- 90% Documents delivered to MSBA – End of February 2013
- 100% Documents delivered to MSBA – End of March 2013
- Contractor mobilization (trailers, fencing, etc.) – Feb/March 2013
- Early construction (enabling work) – Spring 2013
- Building Construction Spring 2013 – March 2015
Spring 2015
Building ready for occupancy (Estimated student move April 2015)
Summer 2015
(Old) building abatement and sitework
Late 2015
Site work complete