Project Timeline

April 2009
Voters approve Master Plan for CCHS

April 2010
Voters approve Feasibility Study and Schematic Design for CCHS

Sept.  2010
CCHS is invited to participate in the Massachusetts School Building Authority’s program for reimbursement June 2011 Feasibility study completed

Aug. 16, 2011
Schematic Design completed and approved by CCHS Building Committee

Aug. 19, 2011
Schematic Design is submitted to MSBA for approval

Sept. 28, 2011
MSBA Board meets and approves CCHS project for funding

Nov. 2011
The towns of Concord and Carlisle vote and overwhelmingly approve CCHS project at Town Meetings and polls

Early 2012
Work begins on Detailed Design, Construction Manager is hired

Aug. 2012
Detailed Design complete, work begins on construction drawings, early bid packages prepared

October 2012
work on Construction Documents begins

Jan-March 2013
Construction starts

      • 60% Documents delivered to MSBA —  End of January 2013
      • 90% Documents delivered to MSBA —  End of February 2013
      • 100% Documents delivered to MSBA —  End of March 2013
      • Contractor mobilization (trailers, fencing, etc.) —  Feb/March 2013
      • Early construction (enabling work) —  Spring 2013
      • Building Construction Spring 2013 – March 2015

Spring 2015
Building ready for occupancy (Estimated student move April 2015)

Summer 2015
(Old) building abatement and sitework

Late 2015
Site work complete