CCHS Building Project Reaches Design Milestone

The CCHS Building Committee reached another important project milestone by advancing the design to 60% construction drawings.  Achieving this milestone and level of detail in the plans allows the team to begin preparing important bid packages for construction materials and construction trades.

These drawings and specification were released to the project estimators in December and the estimating process is nearing completion. The CCHS Building Committee expects to formally submit the 60% drawing package to the MSBA in early February and will quickly follow with the 90% package in early March and the 100% package in early April.   Initial contractor mobilization including fencing, surveying, trailers and limited demolition is expected to begin in early/mid February with full scale site work and earth moving following in March.

 